Reason for Ashton Market work being dug up revealed

WORK on Ashton-under-Lyne’s Market Place is being relaid because it was not good enough. 

And Tameside councillors insist it is not being done at the taxpayers’ expense.

Work on Ashton-under-Lyne’s Market Place has been dug up before the project – with projections it will look like this – has been completed.

Eyebrows were raised when an area of paving on the overrunning multi-million pound project was dug back up. 

But after being asked why by Cllr Kaleel Khan, the authority’s executive member for towns, transport and connectivity, Cllr Stephen Homer, revealed the routine reason. 

And contractors The Casey Group are footing the bill. 

He told the full council meeting on Tuesday, October 6: “Anyone can see it’s gone over. It’s a fact. 

“A lot of the reasons why were totally out of our control, things like problems with utility companies – but there have been problems with some of the workmanship.

Cllr Stephen Homer revealed the action has been taken because of what was deemed to be sub-standard workmanship.

“We want to make sure that marketplace, when it’s finished, is something we can all be proud of. It doesn’t matter what town you’re from within Tameside, we should all be proud of what’s going on in Ashton. 

“We want it to be a place where we can all go, where we can all take our families. We want it to be a safe place, a nice place to go. 

“So when we see workmanship that is not to the highest standard that we want, we go to the contractor and ay, ‘Do it again, but do it at your expense.’ 

“That’s what’s happened. The workmanship was not up to standard, the contractor’s been told it’s not to standard, the contractor’s dug it up, the contractor’s going to put it back down again and it’s ging to be put down at their expense. 

“It’s not going to cost the council tax payer another penny, but it’s going to be done right and that space is going to be fantastic.”